1st Tier Commercial Claimants:
- 1st notice letter to the GC is timely for work done any time after April 1, 2010.
- 2nd notice letter to the GC & Owner is timely for work done any time after March 1, 2010.
- Your mechanic’s lien is timely for work done any time after February 1, 2010.
Residential – 2nd Tier Commercial – Specially Fabricated Claimants:
- Notice letter to the GC & Owner is timely for work done any time after April 1, 2010.
- Your mechanic’s lien is timely for work done any time after March 1, 2010.