December Mechanic’s Lien Deadlines
Commercial Projects
1st Tiered Claimant:
Your notice letters are timely for work done any time after September 1, 2009.
Your mechanic’s liens are timely for work done any time after August 1, 2009.
2nd Tiered Claimant:
Your notice letters are timely for work done any time after October 1, 2009.
Your mechanic’s liens are timely for work done any time after September 1, 2009.
Residential Projects
For all Claimants:
Your notice letters are timely for work done any time after October 1, 2009.
Your mechanic’s liens are timely for work done any time after September 1, 2009.