February Mechanic’s Lien Deadlines
Commercial Projects
1st Tiered Claimant:
Your notice letters are timely for work done any time after November 1, 2009.
Your mechanic’s liens are timely for work done any time after October 1, 2009.
2nd Tiered Claimant:
Your notice letters are timely for work done any time after December 1, 2009.
Your mechanic’s liens are timely for work done any time after November 1, 2009.
Residential Projects
For all Claimants:
Your notice letters are timely for work done any time after December 1, 2009.
Your mechanic’s liens are timely for work done any time after November 1, 2009.