Retainage Claims

*** UPDATE See Law Changes: http://www.kmdalegal.com/construction-law/law-changes-lien-waivers-and-retainage-notices/

Did you know that if you are having any retainage withheld from your draws that you are required to send an additional Retainage Notice?  This is generally ONE notice that gets sent out towards the beginning of the project that protects your rights to lien the retainage later down the line if the Owner or General Contractor fails to pay it.

Like the other Mechanic’s Lien laws, there are specific deadlines you must follow:

  • First Tier-Notice to the Owner by the 15th day of the second month following FIRST MONTH of delivery / work
  • Second and Below Tiers-Notice to the Owner and the General Contractor by the 15th day of the second month following FIRST MONTH of delivery / work.

It seems like lately, and in this declining economy, contractors are “writing off their retainage” more and more frequently.  They are having a harder time getting paid the retainage amounts.  If, you do not want to lose the right to your retainage (which, a lot of times, are quite large amounts), you have to follow the retainage statute.  If you are having any retainage withheld and are not sending a Retainage Notice letter at the beginning of the project, as set forth above, you are not protecting your rights to this money!

A lot of people don’t understand this portion of the mechanic’s lien law.  The best way I can explain it is that the “typical” mechanic’s lien notice letters are not practical for retainage funds that are withheld.  Because most contractors submit multiple payment applications, instead of sending a notice letter every month (because you won’t get paid on the retainage until the completion of the job which is past all bond or lien deadlines), the code allows you to simply send one letter at the beginning of the project to cover all the monies withheld for retainage.  Then, if for some reason you are not paid upon final completion, you can make a bond or mechanic’s lien claim for the retainage amounts AND you have already fulfilled your “notice letter” requirements pursuant to the Texas Property Code.

Without following these rules, you have basically given the GC your retainage. As a matter of fact, I know GCs in Lewisville that count on the fact that you aren’t going to get this right when you contract with them. This is how they are able to underbid city jobs time and time again. Does this sound familiar?

“Paid When Paid” – “Paid If Paid”: Really?

Recently, I had a client that had furnished the supplies and labor on a construction job.  The general contractor on the job failed to pay my client due to the fact that it was not being paid by the owner, attempting to rely on a “paid if paid” clause contained within the subcontract with my client.  Contingent payment clauses are often included in construction contracts to enable one party to avoid making payments to their subcontractors while waiting on payments from an upstream party with the payment obligation.  Contingent payment clauses often have “paid if paid” and “paid when paid” language.

These clauses are highly frowned upon by the courts and typically found to be invalid if the clause is indefinite.  The case law for provisions such as these only goes to timing; the Principal or general contractor cannot withhold payment indefinitely if it is not paid by the Owner.  The clause simply goes to timing of payment, not whether payment will be forthcoming at all.  Gulf Coast, Co., Inc. v. Self, 676 S.W.2d 624, 627-628 (Tex. App. Corpus Christi 1984), writ refused n.r.e., (Mar. 20, 1985).  These clauses may only be relied on for a reasonable amount of time. Id.  It is up to a judge or jury to determine what is “reasonable”.  However, the determination of reasonableness behind clauses such as these, coupled with the Texas Prompt Payment Statute, Texas Property Code Chapter 28, gives us a good starting point as to how long it is considered reasonable to withhold payment.  Texas courts have determined that conditional words such as “if” or “provided that” can be used to enforce clauses such as this. Id.

The Texas Legislature passed a Senate Bill, adding Section 35.521 to the Texas Business and Commerce Code.  Section 35.521 states that a contingent payment clause is not effective against a subcontractor or supplier in the following situations:

1)      If the owner fails to pay the contractor because of the conduct or work of the contractor, unless the nonpayment is the result of the subcontractor or supplier’s failure to meet the needs of the contract.

2)      When the contingent payment clause would be unconscionable if enforced. For example, the contractor must provide the following information to the subcontractor to minimize the possibility of the clause being deemed unconscionable:

  1. Name and contact information of project owner;
  2. Legally sufficient property description;
  3. Surety information; and
  4. Project lenders’ names and contact information.

Further, a contingent payment clause may be invalidated or suspended during the project if the subcontractor subject to the clause has not been paid within 45 days after submitting written request for payment that is in substantial compliance with the pay application, it may send written notice to the contractor objecting to the further enforceability of the clause.  Thereafter, the contractor or its surety may not continue to rely on the clause for any work or material provided by the subcontractor after the notice becomes effective.

With this legislation and case law comes an avenue of collection for subcontractors and suppliers where, in the past, those same subcontractors and suppliers just “wrote it off” if they signed a contract with one of these clauses and didn’t get paid.  Are you owed money on a project that has not been paid because of a contingent pay clause such as the “paid when paid” or “paid if paid” clause?  Now is the time to look into fighting these clauses and collect the money that is owed to you!

October Mechanic’s Lien Reminder

In order to make sure you are filing your mechanic’s lien and notice letters timely, first you really need to know whether or not you are a 1st Tier or 2nd Tier Claimant.
1st Tier Claimant:

  • One who works directly for, or supplies materials directly to, the original contractor
  • Has a contract, written or not, with the original contractor, but not with the owner

2nd Tier Claimant:

  • One who works directly for or supplies directly to any first tier or other lower tier subcontractor
  • Has a contract, written or not, with a first tier or lower tier subcontractor

If you have a contract directly with the Owner, technically, under mechanic’s lien laws, you are considered an original contractor.  Pursuant to the lien laws, the project can have many original contractors on a job.

Once you know what type of Claimant you are refer to the Deadline Chart, within this email, for the current timeline on the lien process which depend on the type of property the work was performed on – Commercial or Residential.

REMEMBER -   IF YOU ARE A 2ND TIER CLAIMANT, YOUR NOTICE LETTERS AND AFFIDAVITS ARE DUE 1 MONTH EARLIER THAN 1st TIERED CLAIMANTS ON COMMERCIAL PROJECTS.

October Deadlines


Commercial Projects

1st Tiered Claimant:

Your notice letters are timely for work done any time after July 1, 2009.
Your mechanic’s liens are timely for work done any time after June 1, 2009.

2nd Tiered Claimant:
Your notice letters are timely for work done any time after August 1, 2009.
Your mechanic’s liens are timely for work done any time after July 1, 2009.

Residential Projects

For all Claimants:

Your notice letters are timely for work done any time after August 1, 2009.
Your mechanic’s liens are timely for work done any time after July 1, 2009.